Campus-Wide Wi-Fi Service

Wi-Fi (wireless network) has become an important way to communicate, collaborate and learn on college campuses.

Vision 2020’s Facilities and Environment Working Group identified Wi-Fi as a required standard for information technology at NIU. ITS is working with the Office of the Provost and Housing to achieve 100 percent Wi-Fi coverage in all student and academic spaces. 

See the Interactive Campus Web Map and choose Wireless Internet under Legend to see current wireless coverage.

Wi-Fi Implementation Schedule

Untitled Document
Deployment Target Date Building Existing Access Points (APs) Vision 2020 APs Additional APs Requested Total APs Deployment Status
Aug '12 Campus Life
2
7
0
9
100% Installed & On-Air
Aug '12 Campus Rec. Center
0
18
0
18
100% Installed & On-Air
Aug '12 Evans Rec. Center
0
6
0
6
100% Installed & On-Air
Aug '12 Founders Library
15
22
0
37
100% Installed & On-Air
Aug '12 Holmes Student Center
19
35
0
54
100% Installed & On-Air
Aug '12 Douglas
21
80
12
92
100% Installed & On-Air
Aug '12 First Year Residence
0
110
0
110
100% Installed & On-Air
Aug '12 Northern View
2
50
0
52
100% Installed & On-Air
Aug '12 Stevenson 
22
102
14
116
100% Installed & On-Air
Oct '12 Art 
5
9
0
14
100% Installed & On-Air
Oct '12 Davis
0
10
12
22
100% Installed & On-Air
Oct '12 DuSable
2
32
5
39
100% Installed & On-Air
Oct '12 Faraday
2
14
15
31
100% Installed & On-Air
Jan '13 McMurry
3
4
0
7
100% Installed & On-Air
Jan '13 Music 
1
23
0
24
100% Installed & On-Air
Jan '13 Psych-Math
4
13
15
32
100% Installed & On-Air
Jan '13 Smart Classrooms (SS 175, DD 30) 0 2 0 2 100% Installed & On-Air
Aug '13 Engineering
4
17
0
21
Installation in Progress
Aug '13 LaTourette 
5
18
9
32
Installation in Progress
Aug '13 Montgomery 
7
8
12
27
Installation in Progress
Aug '13 Reavis
2
7
6
15
Installation in Progress
Aug '13 Wirtz
3
10
6
19
Installation in Progress
Aug '13 Gilbert
0
40
0
40
Part of Building Renovation
Aug '13 Grant D
0
31
0
31
Part of Building Renovation
Aug '13 Lincoln
22
90
TBD
90
Planning Phase
Aug '13 Neptune
25
92
16
108
100% Installed & On-Air
Jan '14 Stevens
0
11
TBD
11
Part of Building Renovation
Jan '14 Still Hall
2
4
0
6
Planning Phase
Jan '14 Still Gym
0
6
0
6
Installation in Progress
Jan '14 Watson 
2
8
7
17
Planning Phase