Partnership School Building Improvements
Required Items
| Raise music room floor level (or possible ramp) |
20,000 |
| Install Handicapped Accessible drinking fountains |
10,000 |
| Handicapped lift/ramp down to gym floor/side door concrete stoops |
60,000 |
| Replaced interior doors/door hardware/5'-0" door opening |
48,000 |
| Reduced pressure back flow prevented on water service |
10,000 |
| Provide age appropriate sinks in 4 classrooms |
10,000 |
| Remove asbestos floor tile/install new vinyl compositions tiles |
65,000 |
| Remove asbestos plaster ceiling/install new acoustic tile ceiling |
80,000 |
| Install toliet/sink in kindergarten rooms |
25,000 |
| Install emergency lighting |
10,000 |
| Upgrade electrical service |
40,000 |
| Interior wall finishes (3,600sf@$15/sf) |
54,000 |
| Replace broken unit ventilators throughout school |
200,000 |
| Total |
632,000 |
| Multiplier (contingency, FFE A/E fee, 1% Admin) |
170,640 |
| Total Required Items |
802,640 |
Alternative bid items
| Replacement/upgrade of select lighting areas |
40,000 |
| Tuck pointing |
20,000 |
| Install new intercom system |
105,000 |
| Replace main boiler |
200,000 |
| Total |
365,000 |
| Multiplier (contingency, FFE A/E fee, 1% Admin) |
98,550 |
| Total alternative bid items |
463,550 |
| |
|
| Total Required Items and Alternative bid items |
1,266,190 |