updated 8/28/13

SiteWork DescriptionStartAnt. Comp.
Neptune Central Drive Cut and patch road 6/3/2013 6/5/2013
HSC Bus turn around Cut and patch road 6/3/2013 6/5/2013
Music Building north lot Cut and patch road 6/3/2013 6/5/2013
Lot V entrance (Anderson) Cut and patch road 6/3/2013 6/7/2013
Kish drive bus turn around Cut and patch road 6/25/2013 6/27/2013
Stadium drive east (multiple sections) Cut and patch road 6/6/2013 6/7/2013
North of Television center entry Cut and patch road 6/5/2013 6/5/2013
Stadium Drive West (across from transportation) Cut and patch road 6/6/2013 6/7/2013
Grant Access Road Cut and patch road 6/6/2013 6/7/2013
East Heating Plant (east side) Cut and patch road 6/3/2013 6/5/2013
Stadium Drive South (west half only) Cut and patch road 6/25/2013 6/28/2013
University Circle Replace 4" of asphalt binder and surface over compacted gravel base. 7/22/2013 8/5/2013
Dorland Receiving Entrance Drive & Approach (east half only) Replace 4" of asphalt binder and surface over compacted gravel base. 7/12/2013 7/12/2013
Physical Plant (south and southeast) Replace 4" of asphalt binder and surface over compacted gravel base. 7/22/2013 7/30/2013
Satellite Buildings Patch, fill cracks, and seal 6/11/2013 6/14/2013
Stadium Drive W. Road construction 6/10/2013 8/20/13
Grant Drive E. & Lincoln Drive N. Road Construction 6/17/2013 7/30/13