SITEWORK DESCRIPTIONSTARTANT. COMP.
Lowden Hall Kiosk nearby on College Ave. 6/1/14 Complete
Psych/Math Bridge Paint exterior 7/17/14 Complete
Founders and Swen Parson Walkway 7/24/14

Complete
7/25/14

Campus wide Fire hydrants 8/1/14 8/15/14
Still Hall Paint fire escape 8/15/14 9/1/14
Still Gym Paint fire escape 8/15/14 9/1/14
Davis Hall West side (continued from FY13) 6/1/14 Complete
Northern View Exteriors (continued from FY13) 5/12/14 Complete
7/10/14
Recreation Center Exposed concrete on lower portion (where black waterproofing is) 8/1/14 9/1/14
Campus wide Silver handrails around the West Lagoon, Grant C and D, Chessick Practice Center 5/19/14 Complete
7/10/14
Health Services Paint building exterior & caulk windows 5/19/14 Complete
7/24/14
Physical Plant Paint building exterior to match HR building 8/15/14 8/29/14
Williston Paint fire escape 7/15/14 Complete
7/24/14
Monat Block addition 8/15/14 9/1/14
Montgomery Trim 6/15/14 8/15/14
Faraday/Montgomery Paint bridge 8/15/14 9/1/14