Exterior Cleaning

updated 8/19/14

SITEWORK DESCRIPTIONSTART ANT. COMP.
Still Hall Still Hall touch up roof line 6/9/14 Complete
6/10/14
Faraday Faraday West roofline 6/2/14 Complete
6/3/14
Lincoln Clean mold 6/12/14 Complete
6/23/14
Music Library Music Library entrance 6/5/14 Complete
6/5/14
Neptune Central Neptune Central South wall above pit area (mold) 7/30/14 Complete
7/30/14
Wirtz Wirtz bridge 6/3/14 Complete
6/5/14
HSC HSC clean limestone panels 6/12/14 Complete
8/11/14
La Tourette La Tourette top turns black but bad water problems
Visual Arts Power wash 6/6/14 Complete
6/6/14
Music Building Power wash courtyard 7/25/14 Complete
7/31/14
Anderson South entrance 8/1/14 Complete
8/1/14
Anderson West entrance 8/1/14 Complete
8/14/14
Anderson Power wash dock entrance 8/8/14 Complete
8/8/14
Anderson Power wash courtyard 8/8/14 Complete
8/13/14
Convocation Center Power wash entrance 5 8/6/14 Complete
8/6/14
Parking Garage Parking Garage windows 5/19/14 Complete
5/22/14
IASBO IASBO windows 7/8/14 Complete
7/8/14
Black Studies Black Studies windows
Psych Math Psych Math windows 7/7/14 In progress
Founders Library Founders windows 5/19/14 In progress
Anderson Anderson windows 6/27/14 In progress
Engineering Engineering windows 6/30/14 In progress
Barsema Barsema windows 6/27/14 In progress
Campus Life Campus life windows 7/16/14 Complete
7/17/14
Music Building Music Building windows 6/25/14 In progress
Alumni Center Alumni windows 5/22/14 Complete
5/23/14
Huskie Stadium Stadium windows 5/23/14 Complete
5/23/14
Yordon Yordon windows 5/27/14 Complete
5/28/14
Lincoln Lincoln windows
Neptune Neptune windows 7/29/14 Complete
7/30/14
La Tourette La Tourette windows 5/23/14 Complete
7/24/14
Davis Davis windows 8/6/14 Complete
8/7/14
Swen Parson Swen windows 5/21/14 Complete
5/23/14
Altgeld Altgeld windows 6/13/14 Complete
7/18/14
Lowden Lowden windows 6/12/14 Complete
6/18/14
Faraday Faraday windows 6/2/14 Complete
7/21/14
Montgomery Montgomery windows 7/3/14 Complete
8/4/14
Still Hall Still hall windows 6/24/14 Complete
6/25/14
Still Gym Still Gym windows 6/24/14 Complete
6/24/14
Visual Arts Art building windows 6/26/14 Complete
6/27/14
Adams Adams windows 8/8/14 Complete
8/8/14
Williston Williston windows 6/6/14 Complete
6/12/14
Reavis Reavis windows 6/2/14 Complete
6/3/14
DuSable DuSable windows 5/20/14 Complete
5/21/14
Cole Cole windows 6/2/14 Complete
6/5/14
Zulauf Zulauf windows 6/5/14 In progress
Graham Graham windows 5/21/14 Complete
6/2/14
Gabel Gabel windows 5/31/14 In progress
Field House Field House N windows 5/29/14 Complete
5/29/14
Dorland Dorland windows 5/28/14 Complete
5/28/14
Violence Center Violence Center windows 7/15/14 Complete
7/16/14
Health Services Health Services windows 5/15/14 Complete
5/22/14
Woman's Resources Woman's Resource windows 7/28/14 Complete
7/28/14
Chiller Plant Chiller Plant windows 7/28/14 Complete
7/28/14
Northern View Northern View windows 7/2/14 Complete
7/15/14
HSC Student Center windows 8/11/14 8/13/14
Grant & Stevenson Grant and Stevenson towers
Chessick Center Chessick Practice Center windows 5/28/14 Complete
5/28/14
Watson Watson windows 6/3/14 In progress
Wirtz Wirtz windows 6/23/14 Complete
6/25/14
McMurry McMurry windows 6/26/14 Complete
6/27/14